>>10246597Commissioning of two new production lines The operations and commissioning of the Company’s two new lines have been affected by supplier re-alignment and fine-tuning problems. Since both new lines are under warranty, the operations of the two new lines can only commence after the suppliers’ adjustments are completed. As the services of the suppliers fall under the non-essential sector affected by the MCO, these relatively minor adjustments cannot be remedied until after lifting of the MCO. According to the current Malaysian Government directive, the MCO is effective until 28 April 2020